The former Portland Gasworks site at 25 Glenelg Street is undergoing an important environmental restoration to remove historical pollution and make the land safe for potential future use.
AusNet has engaged Ventia, a highly experienced environmental remediation contractor, to carry out clean-up works between August 2025 and mid-2026.
This work is being delivered under strict EPA Victoria guidelines, with independent environmental consultants and an accredited auditor supervising the process.
The remediation project will be completed in five stages:
Early works are scheduled to begin in late August 2025 and will prepare the site for the main restoration activities. These works will include:
These activities will be carried out within the approved working hours and managed to minimise impacts on the local community.
A copy of our community notification can be found here.
While every effort will be made to reduce impacts on residents, businesses, and the local community, there may be times where disruptions are unavoidable.
Here’s what you can expect:
AusNet and Ventia are committed to keeping the community informed and involved throughout the project. Signage, regular updates, and community feedback opportunities will be available
AusNet and Ventia are committed to keeping the community informed and involved throughout the project.
To get in touch with our team you can contact us via any of the methods here